- Building Information
Viel-Arcy
(Aisne, France)
Saints-Pierre-et-Paul
Surveyed: 1980-83, 2003, 2015
- Locator Map
Viel-Arcy (Aisne, France) - Saints-Pierre-et-Paul
- Disclaimer
The dating found here is based on the work of John James, and is meant on this site to serve as a starting point. James' dating is derived from a system that uses his interpretation of the development of capitals over time as the basis for chronology, among other factors. His goal is to refine the dating to within years rather than decades. I have not fully embraced James' methodology, and will be developing this page from its current state to one which is admittedly more conservative. The relative expenditure values found in the Timeline are also based on James' work, and I believe these to be reasonably reliable. They are intended only to give a sense of the amount of work involved in each decade.

I have added the idea of the "project" as a way of separating work in buildings. In my mind, a "project" is a discrete section of work in a building that resulted from the one-time acquisition of funding. "Projects" are generally separated by at least a decade where no work was being done. It is my view that it would have been unwise to start a "project" that could not be finished and protected from the elements, and as such a "project" usually involved a wing or multiple wings of a building, from floor to roof. Rural churches, which could only secure small amounts of funding at irregular intervals, often were the result of many small projects, while the great churches, which benefitted from relatively consistent funding, may have involved only a few large projects.
- Timeline with Relative Expenditure (if available, in building units)



- Project A - 1110s - Phase 1 - apse (d)
Apse dado, crossing and tower base with pilaster for nave with taller piers; there were openings into small lateral chapels, now rebuilt;
- Project A - 1110s - Phase 2 - apse (a)
Apse to vaults and cornice; the apse windows are curved on outside but straight on inner face.
- Project A - 1120s - Phase 3 - tower II
Upper tower, since rebuilt
- Project A - 1120s - Phase 4 - nave
Nave and west door with lower piers, but no walls to the aisles, and with extension for north aisle.
- Project B - 1200s - Phase 5 - north
North arm with about 4 courses of lower aisle wall butted into earlier work both ends.
- Project C - Later - Phase 6 -
South arm, complete upper walls to aisles
- Primary Sources for Dating
There are no primary source documents for this building