Épône (Yvelines, France) - Saint-Béal
- Disclaimer
The dating found here is based on the work of John James, and is meant on this site to serve as a starting point. James' dating is derived from a system that uses his interpretation of the development of capitals over time as the basis for chronology, among other factors. His goal is to refine the dating to within years rather than decades. I have not fully embraced James' methodology, and will be developing this page from its current state to one which is admittedly more conservative. The relative expenditure values found in the Timeline are also based on James' work, and I believe these to be reasonably reliable. They are intended only to give a sense of the amount of work involved in each decade.
I have added the idea of the "project" as a way of separating work in buildings. In my mind, a "project" is a discrete section of work in a building that resulted from the one-time acquisition of funding. "Projects" are generally separated by at least a decade where no work was being done. It is my view that it would have been unwise to start a "project" that could not be finished and protected from the elements, and as such a "project" usually involved a wing or multiple wings of a building, from floor to roof. Rural churches, which could only secure small amounts of funding at irregular intervals, often were the result of many small projects, while the great churches, which benefitted from relatively consistent funding, may have involved only a few large projects.
I have added the idea of the "project" as a way of separating work in buildings. In my mind, a "project" is a discrete section of work in a building that resulted from the one-time acquisition of funding. "Projects" are generally separated by at least a decade where no work was being done. It is my view that it would have been unwise to start a "project" that could not be finished and protected from the elements, and as such a "project" usually involved a wing or multiple wings of a building, from floor to roof. Rural churches, which could only secure small amounts of funding at irregular intervals, often were the result of many small projects, while the great churches, which benefitted from relatively consistent funding, may have involved only a few large projects.
- Timeline with Relative Expenditure (if available, in building units)
- Project A - 1090s - Phase 1 - tower base
Tower base with entry door in five campaigns, probably groin vaulted.
- Project B - 1120s - Phase 2 - nave entry
- Project B - 1130s - Phase 3 - tower I
Tower first level against an earlier nave as not all shafts carved on S and SW side.
- Project B - 1130s - Phase 4 - tower II
Second level of tower and possibly the first octagonal tower in northern France.
- Project B - 1130s - Phase 5 - tower III
Third level of tower to same arrangement as the second
- Project C - 1160s - Phase 6 - spire
One of the Galeran spires on octagonal two-stories from just over the openings in the level below.
- Project D - 1200s - Phase 7 - apse
Two apse bays, though much replaced with vault inserted under tower possibly at the same time.
- Primary Sources for Dating
There are no primary source documents for this building